| ID | Action Number | Title | Description | Priority | Due At |
|---|---|---|---|---|---|
| 1 | CA-2026-0501 | Separate lift supervision from working supervision | Appoint a dedicated lift supervisor for all crane ... | CRITICAL | 2026-08-15 00:00 |
| 2 | CA-2026-0502 | Re-brief all crews on exclusion zone requirements | Toolbox brief covering CTL-01 performance requirem... | HIGH | 2026-08-12 00:00 |
| 3 | CA-2026-0503 | Install toe boards and containment at the crusher ... | Fit toe boards and debris netting to prevent objec... | HIGH | 2026-08-20 00:00 |
| 4 | CA-2026-0504 | Weekly contractor competency currency report | Torrens to provide a weekly competency currency re... | MODERATE | 2026-10-31 00:00 |
| 5 | CA-2026-0505 | Permanent signage for the alternate walking route | Replace temporary signage with permanent signage a... | LOW | 2026-08-29 00:00 |